Skip links and keyboard navigation

Construction notifications

Construction notifications are issued for works across the project. See below for details of the latest works on the Gateway Upgrade North.

Subscribe

To receive regular project updates, find out more about consultation activities, and keep up to date with construction and traffic impacts once works commence, register your details here.

 

Latest notifications

31 March – Sandgate Road bridges works update

Deconstruction of the existing northbound bridge over Sandgate Road/Braun Street and the Shorncliffe rail line began successfully during March, with approximately one third of the above-ground elements of the structure already removed.

Find out more about works in April.

29 March – Nudgee Road interchange and Nundah Creek works update

Day and night work will be ongoing during April/May to upgrade the Nudgee Road interchange and widen the Gateway Motorway bridges over Nundah Creek.

Find out more information

20 March – Works update: Road pavement and safety improvements, Bracken Ridge to Bald Hills

As part of the Gateway Upgrade North project, road pavement rehabilitation work and safety improvements are being undertaken on the motorway between the Deagon Deviation and Wyampa Road overpass.

Find out more information

13 March – Works update: Bridge construction activities at Depot Road, Deagon

From late March 2017, night works will recommence to install the five remaining concrete bridge foundations (called piles) required to widen the southbound Gateway Motorway bridge over Depot Road, Deagon.

Find out more information

27 February – Changes to Nudgee Waterhole Reserve

Permanent upgrades are being made to Nudgee Road and Childs Road as part of the Gateway Upgrade North project. As part of these upgrades, changes are being made to facilities in and around the Nudgee Waterhole Reserve.

Find out more information

13 February – Drainage installation works at Deagon

As part of works to upgrade Depot Road from two lanes to four between Braun Street and the Gateway Motorway ramps, a major upgrade of the Depot Road/Braun Street/Board Street/Deagon Deviation intersection is being undertaken. To facilitate this upgrade, from mid-February 2017 for approximately two months, works will be undertaken to install new underground drainage lines at the intersection.

Find out more information

2 February – Works update: Deagon Deviation widening and bridge construction works

Works to widen the Deagon Deviation between Depot Road and Bracken Ridge Road, and construction of the new Deagon Deviation bridge over the Gateway Motorway are progressing well. These construction activities will continue throughout 2017 and into 2018.

View more information

20 January – Temporary pathway closure: Gateway Motorway between Depot Road and John Fisher Drive

From late January 2017 until mid-2017, sections of the shared pathway located alongside the northbound lanes of the Gateway Motorway, between Depot Road, Deagon and John Fisher Drive, Bracken Ridge, will be temporarily closed to all users intermittently.

View more information

20 January – Gateway Motorway bridge widening at Bicentennial Road interchange

The first stage of work to widen the Gateway Motorway bridges over the Bicentennial Road interchange was completed in late 2016, with the two widened northbound bridges now open to traffic.

The next stage of work involves widening the two southbound bridges which will begin in late January 2017 and is expected to be complete by early 2018.

Find out more information

15 December – Extended temporary shared pathway closure at Boondall

Due to ongoing bridge construction works on the Gateway Motorway over Sandgate Road/Braun Street and the Shorncliffe rail line, a section of the shared pathway between Boondall Train Station and the Cabbage Tree Creek pedestrian/cycle bridge will remain temporarily closed to all users until late 2017.

View detour information

12 December – Shared pathway diversion at Bracken Ridge

From Monday 19 December 2016 until mid-2017, a section of the shared pathway located alongside the northbound lanes of the Gateway Motorway, between Barrett Street and John Fisher Drive in Bracken Ridge, will be temporarily closed to all users.

View detour information

17 October – Energex tower works at Boondall and Taigum

Works are being undertaken to construct a new high voltage Energex pole on the eastern side of Cabbage Tree Creek, and to realign overhead wires over the Gateway Motorway between Boondall and Taigum.

Find out more information

12 August – Depot Road works: Braun Street to the Gateway Motorway ramps

As part of the Gateway Upgrade North project, Depot Road is being upgraded from two lanes to four between Braun Street and the Gateway Motorway ramps. Works will be undertaken in stages from mid-August until late 2018.

Find out more about these works

Last updated
30 March 2017