Skip links and keyboard navigation

Construction notifications

Construction notifications are issued for works across the project. See below for details of the latest works on the Gateway Upgrade North.

Subscribe

To receive regular project updates, find out more about consultation activities, and keep up to date with construction and traffic impacts once works commence, register your details here.

Latest notifications

28 May – Nudgee Road interchange and Nundah Creek works update

Day and night work will be ongoing during June/July to upgrade the Nudgee Road interchange and widen the Gateway Motorway bridges over Nundah Creek.

Find out more information

23 May – Changes to Nudgee Waterhole Reserve parking

Permanent upgrades are being made to Nudgee Road and Childs Road as part of the Gateway Upgrade North project. To enable these upgrades, access to the Nudgee Waterhole Reserve will temporarily change.

In mid May 2017 for approximately six months, the Nudgee Waterhole Reserve car park on Nudgee Road will be temporarily closed. Alternate parking is available next to the Banyo Football Club on Childs Road.

Find out more information

14 May – Nudgee Road traffic changes

As part of the Gateway Upgrade North project, the Nudgee Road interchange is being upgraded, including the construction of a new Nudgee Road bridge over the Gateway Motorway and extended on and off-ramps. To connect to the new bridge, Nudgee Road is being permanently realigned and when complete, will include a signalised intersection at the new southbound on and off-ramps.

Find out more information

10 May – Works update: Deagon Deviation bridge construction and Depot Road on and off-ramp realignment

Works to construct the new Deagon Deviation bridge over the Gateway Motorway, connecting northbound traffic onto the Deagon Deviation towards Redcliffe, are progressing well. The first bridge beams were installed during April 2017 and the first section of bridge deck is now under construction.

Find out more information

9 May – Earthworks and drainage for new shared pathway: Sandgate Road, Boondall to Muller Road, Taigum

From mid-May 2017, earthworks and drainage work will begin between Sandgate Road, Boondall and Muller Road, Taigum to enable construction of the permanent shared pathway at this location.

Find out more information

28 April – Sandgate Road bridges works update

Deconstruction of the existing northbound bridge over Sandgate Road/Braun Street and the Shorncliffe rail line is progressing well, with approximately two-thirds of the above-ground elements of the structure now removed

Find out more about works in May

20 March – Works update: Road pavement and safety improvements, Bracken Ridge to Bald Hills

As part of the Gateway Upgrade North project, road pavement rehabilitation work and safety improvements are being undertaken on the motorway between the Deagon Deviation and Wyampa Road overpass.

Find out more information

13 March – Works update: Bridge construction activities at Depot Road, Deagon

From late March 2017, night works will recommence to install the five remaining concrete bridge foundations (called piles) required to widen the southbound Gateway Motorway bridge over Depot Road, Deagon.

Find out more information

13 February – Drainage installation works at Deagon

As part of works to upgrade Depot Road from two lanes to four between Braun Street and the Gateway Motorway ramps, a major upgrade of the Depot Road/Braun Street/Board Street/Deagon Deviation intersection is being undertaken. To facilitate this upgrade, from mid-February 2017 for approximately two months, works will be undertaken to install new underground drainage lines at the intersection.

Find out more information

20 January – Temporary pathway closure: Gateway Motorway between Depot Road and John Fisher Drive

From late January 2017 until mid-2017, sections of the shared pathway located alongside the northbound lanes of the Gateway Motorway, between Depot Road, Deagon and John Fisher Drive, Bracken Ridge, will be temporarily closed to all users intermittently.

View more information

20 January – Gateway Motorway bridge widening at Bicentennial Road interchange

The first stage of work to widen the Gateway Motorway bridges over the Bicentennial Road interchange was completed in late 2016, with the two widened northbound bridges now open to traffic.

The next stage of work involves widening the two southbound bridges which will begin in late January 2017 and is expected to be complete by early 2018.

Find out more information

15 December – Extended temporary shared pathway closure at Boondall

Due to ongoing bridge construction works on the Gateway Motorway over Sandgate Road/Braun Street and the Shorncliffe rail line, a section of the shared pathway between Boondall Train Station and the Cabbage Tree Creek pedestrian/cycle bridge will remain temporarily closed to all users until late 2017.

View detour information

12 December – Shared pathway diversion at Bracken Ridge

From Monday 19 December 2016 until mid-2017, a section of the shared pathway located alongside the northbound lanes of the Gateway Motorway, between Barrett Street and John Fisher Drive in Bracken Ridge, will be temporarily closed to all users.

View detour information

12 August – Depot Road works: Braun Street to the Gateway Motorway ramps

As part of the Gateway Upgrade North project, Depot Road is being upgraded from two lanes to four between Braun Street and the Gateway Motorway ramps. Works will be undertaken in stages from mid-August until late 2018.

Find out more about these works

Last updated
25 May 2017